Friday, September 20, 2013

Garage Progress

We've been making slow progress on the garage. Because of the tremendous amount of local housing construction, our little project hasn't been high on our subs priority list. It's taken a few weeks longer than expected, but here's what's been going on...

We had the soil dug up for the grade beam. This frost wall is super important up here where we have lots of freeze/thaw cycles that can compromise the structure. The bobcat accidentally hit the line for our outdoor electrical panel but, thankfully, it didn't do too much damage and was a quick fix for our good buddy the electrician.



Next up, the foundation forms and re-bar for our concrete. Once this passed inspection, we had the grade beam poured.






Next was our garage pad. We had to remove an existing basement window (local code won't allow this opening once the garage is up) and the sill sat below the finished pad, so it had to go. I asked the contractor to give the pad a brushed finish so the epoxy I plan to apply will adhere better. Because the pad was a few inches higher than our patio, they created a rounded transition from the garage door.





The rest of the garage went up pretty quickly. The trusses were delivered right on time and the guys got to work. Before we knew it, we had walls and a roof! This is the point where I got the most excited, it really is going to make an awesome area for my workshop.





The original soffit and fascia on the rear are still in place, and I think I may just leave it. The ceiling will eventually be drywalled so it won't be seen anyway. The existing garage door will be removed and reinstalled at the entrance to the new addition and we'll remove the existing light fixture.



The electrician comes tomorrow to rough in our lighting and indoor and outdoor outlets...time to shop for an outdoor fixture! The original was just too small for the space and really didn't shed much usable light. Because this rear light will now provide light to the east side of the patio, I want it to be more practical.

Our exterior contractor is super busy and is going to squeeze this job in as soon as he can, he's on deck for next week. Stay tuned for more!

When You Just Can't...

Trying to maintain my blog over the past few years has been a real challenge for me. It's gotten harder as my mom, who was battling diabetes, heart disease and kidney failure, relied more and more on me to take on the responsibility for her personal and financial affairs.

It's been a very long road for our family as mom fought these diseases...they are brutal and show no mercy.

Between the day to day of life, and the responsibilities I took on for my mom...there was just nothing left for this blog. I'd try...but just couldn't.

Mom's brave fight for life ended on September 5th, and it's left me reeling. But, it's also released the enormous pressure I put on myself to focus on her needs, instead of my own.

I miss my mom terribly. Those who have been through it can understand that there are no words to describe the emotions involved when a parent dies. But I know that she'd hate for me to dwell on that sadness.

So, I've decided to dedicate this humble little blog to my mom. She always got a kick out of all the crazy projects I had on the go. She was hugely supportive of this blog, and I want to ensure that she stays proud of me for not giving it up.


Thanks for sticking with me!

Friday, August 2, 2013

Garage Addition Saga

In construction it seems that, no matter how much you plan, things will inevitably go awry.

I posted quite a while back about our garage addition and the construction quote I was waiting for. When the quote came in, it was high. Much, much higher than I had hoped. It immediately put this project on hold.

After feeling sorry for myself for a few months, I called up my cousin (a custom builder) to see if he could help me out (or at least call in a few favours with his subs to save me some moolah). I didn't expect him to take on this project himself. He builds very high end homes, and I knew that my little 14' x 19' garage addition wasn't something that he'd likely be interested in taking on.

Much to my surprise, he offered to have his crews complete it for me for less than half what other contractors had quoted me. Yes, you read that right...less than half! The catch was that we would have to find someone to complete the exterior.

Quick like a bunny, our architect complete drawings, the engineer finished the foundation drawings, and I had building permits from the town.




That's when things got frustrating...

The engineer required enormous footings for this addition. Much larger than were required, in our opinion. It almost doubled the cost of the build in concrete alone. It also would have required us to tear out half of my brand new patio and create a huge mess which would drive my neighbours nuts. There had to be another way....

After a lot of discussion with the engineer, he agreed that we could use 3 1/2" x 16' screw piles for the foundation (traditional concrete piles were not an option for us; our soil is far too sandy to drill as deep as we needed, and it still would have been a messy job). We still had to cut the patio, but only 12", I could live with that. Armed with this new set of foundation drawings, I had to submit an amendment to our building permit.



Tick tock.

Thing is, folks, 16' screw piles are hard to come by, and we ended up having to have them custom manufactured.

Tick tock.

Yesterday, these piles finally got installed. It is a slick process. It's super simple, the guys were hilarious, and they had all 5 in place in less than 3 hours. After all the drama, I was so happy to get this show on the road!









 
As long as the weather holds, we can expect the grade beam to be poured next week. Then walls and roof...we could have a closed in garage in less than 2 weeks!
 
 



Wednesday, May 29, 2013

Main Floor Custom Cabinet

One of the few regrettable decisions I made during the construction of our house was removing a 3-sided fireplace between the living room and dining area of the main floor. The intent was to open up the space but it backfired...now it's too open! The result has come to be known as "No Man's Land".


Right now, No Man's Land is home to a curio cabinet I got from a friend, that's become a catch all for random accessories and books. Needless to say, something has to be done!

I stumbled on a local craftsman who does amazing custom woodwork, and challenged him to come up with a solution to my problem.
His cabinet design is approx. 3' x 5' x 4'. Big enough to fill up this empty space and provide us with storage, but not so big that it overwhelms the house.




I love it and can't wait to see it finished!


Tuesday, May 7, 2013

More Than I Could Chew

You know that saying? The one about biting off more than you can chew? Yeh, that pretty much sums up my adventures in landscaping.

Last summer, Mr. Mel and I did alot of work, ALOT of work by ourselves. I did my own landscape plan, we hauled, shoveled, lifted, dug, mulched....but there is still plenty of work to be done to get the yard to a place that I'd consider "done".

This project is just too big for me to get done without help, so Mr. Mel and I have hired a professional landscaper to finish what we started. The control freak in my is having a meltdown. But at the same time I think it's important to recognize when we're in over our heads, and to ask for help.

We will still be getting our hands dirty, but I'm looking forward to having a pro fix and problem solve some areas that I lack the knowledge to tackle on my own.

Our front yard has a steeper grade than I realized that must be retained and have levels built in. This is way beyond what I am comfortable handling on my own. The overall design for the front yard will stay as-is, but we will have stone edge installed to hold in our soil and mulch (which seems to run off during every rain) and to provide a finished edge against the sod.

The front patio will be moved further out from the house and will be made about 4 feet larger, and a planter and pergola will be built for shade and interest.

Switzer's Nursery & Landscaping

They'll also be grading near the road to create a more gradual ditch that will be much easier to mow.

Many of our cedars and a few other plants didn't or barely survived the harsh winter (and hungry rabbits and deer), so the landscaper will be replacing some and relocating others.

Our subdivision was pasture land for many decades and, as a result, there are some very stubborn weeds and grasses that will take a few years to permanently kill off. They'll also be hauling in yards and yards of mulch to fill up the beds and help control the weeds.

The backyard will get new brick flower bed edging, mulch, some grading work, and a stacked stone seating wall around the patio and built in bbq area.


For the front and rear yards we'll get detailed planting plans that we can follow over the next few years to fill in our beds as we kill off our wild weeds and grasses.

I'm excited to share photos as this project gets underway.